Reference Project — Kyrgyzstan

A 500 kg/h Short-Cut Pasta Line Built from Scratch in Kyrgyzstan

An investor in Kyrgyzstan wanted to build a pasta factory from scratch, with no prior experience in pasta production. In 2008 the company commissioned Talia Makina's 500 kg/h turnkey short-cut line. The installation is one of the first turnkey projects of Talia Makina, founded in 2007; the line has been in production for 18 years.

1 LineTurnkey short-cut
500 kg/hTheoretical 12 tons/day
2008Commissioning · one of our earliest references
24 MonthsStandard warranty

Producer and Line Details

Installed Line — 2008500 kg/h short-cut lineFrom raw-material dosing to drying and the final product, the process runs under Siemens PLC control, with Siemens components in the panels as well. In continuous operation the theoretical capacity reaches 12 tons per day.
Project ProfileA pasta plant from scratchThe investor had no prior experience in pasta production; the goal was to build a pasta plant from scratch. The entire process, from line design to operator training, was handled by Talia Makina from a single source.
From 2008 to TodayOne of our first projectsThis installation is one of the first turnkey projects of Talia Makina, founded in 2007. Commissioned in 2008, the line has been in production for 18 years and is one of the first links in a reference network that now spans 18 countries.

Project Story

In 2008, an investor in Kyrgyzstan wanted to build a pasta plant from scratch. With no prior experience in pasta production, the company was not looking for a supplier that delivers the machinery and leaves, but for a turnkey partner that builds the plant and brings it to production readiness.

The project was realized with Talia Makina's 500 kg/h short-cut pasta line: line design, manufacturing, shipment, on-site installation, commissioning and operator training were carried out from a single source. This installation is one of the first turnkey projects of Talia Makina, founded in 2007.

The line runs on Siemens PLC-based automation, with Siemens components in the panels as well. All product-contact surfaces are made of food-grade AISI 304 stainless steel. The line produces a wide range of short-cut pasta shapes; a round-die change yields dozens of different shapes on the same line. In continuous operation the theoretical capacity reaches 12 tons per day.

In a plant built from scratch, the most critical stage is preparing the team for production: during commissioning, hands-on operator training was delivered on site and the first production period was supervised. Thanks to recipe-based automation, even an inexperienced team reached consistent production quality in a short time.

Commissioned in 2008, the line has been in production for 18 years and ranks among Talia Makina's longest-running references. Our presence in Central Asia did not stop there: in neighboring Uzbekistan we have installed seven lines across three factories since 2014. Kyrgyzstan is one of the first links in the turnkey installations we have delivered in 18 countries since 2007.

Project Fact Sheet

CountryKyrgyzstan
Project StructureA plant built from scratch; single-line turnkey installation — one of our first projects
Line TypeShort-cut
Capacity500 kg/h · theoretical 12 tons/day
Commissioning2008
AutomationSiemens PLC; Siemens components in the panels
ProductsA wide range of short-cut shapes — dozens of shapes via die change
Body MaterialFood-grade AISI 304 stainless steel
Warranty24-month standard warranty

Turnkey Project Steps

Line DesignLayout and process flow based on capacity and product range
ManufacturingProduction at our Gaziantep facilities with AISI 304 bodywork
On-Site InstallationMechanical and electrical installation at the factory in Kyrgyzstan
CommissioningTuning of production and drying parameters, trial production
Operator TrainingHands-on training on site and production supervision

Project Results

The goal of a pasta plant from scratch was achieved with the turnkey model
500 kg/h installed capacity · theoretical 12 tons/day
In production since 2008 — one of our longest-running references
One of Talia Makina's first turnkey projects
An inexperienced team was prepared for production with training and supervision
Complete Siemens automation infrastructure (PLC + components)
A wide range of short-cut shapes on a single line
AISI 304 stainless steel on all product-contact surfaces

Frequently Asked Questions

How is a pasta production line installed in Kyrgyzstan?

Project planning, line design, manufacturing, shipment, on-site installation, commissioning and operator training are delivered turnkey from a single source. The full scope was applied in the Kyrgyzstan installation; the line entered production in 2008.

What capacity was installed in Kyrgyzstan?

A 500 kg/h short-cut pasta line was installed. In continuous operation the theoretical capacity reaches 12 tons per day.

Which pasta shapes are produced?

A wide range of short-cut shapes is produced; a round-die change yields more than 30 shapes on the same line.

Where should an investor start when building a pasta factory from scratch?

The first step is capacity selection and a line layout plan based on the target market. In the turnkey model, line design, manufacturing, installation, commissioning and operator training proceed from a single source, so the investor does not need to build a machinery engineering team. Our customer in Kyrgyzstan started production from scratch with this model in 2008.

Can an investor with no pasta experience operate the line?

Yes. During commissioning, hands-on operator training is delivered on site and the first production period is supervised; since production parameters are stored in PLC recipes, product quality does not depend on operator experience. The plant in Kyrgyzstan reached consistent production in a short time even though the team had no prior pasta experience.

How long do Talia Makina lines keep running?

The line in Kyrgyzstan has been in production since 2008, the line in Ukraine since 2013 and the first line in Uzbekistan since 2014. With regular maintenance and original spare parts, the lines run efficiently for well over 15 years.

What automation infrastructure does the line use?

Siemens PLC-based automation is used, and the panel components are Siemens as well. Process and recipe management from raw-material dosing to drying runs automatically.

What does the warranty cover?

All our lines are delivered with a 24-month standard warranty covering parts and workmanship. After the warranty, our spare-parts supply and technical support program continues.

Does Talia Makina have other installations in Central Asia?

Yes. In neighboring Uzbekistan, seven lines have been installed across three separate factories since 2014 (six in operation, the seventh being commissioned in September 2026). Together with the 2008 installation in Kyrgyzstan, Central Asia is one of our longest-standing reference regions.